WORK ACCOMPLISHED
- BUILDINGS AND GROUNDS - 6/2/18 - Our picnic table was put out. Tony policed grounds for trash.
6/3/18 - Nestor cut the grass along the parking lot fence and next to the Guardhouse. Nestor, Mike and his crew lifted the speeder and rail trailer and placed them on the display track next to the back entrance.
6/5/18 - Nestor weed-wacked by the display cars. Steve cut the back grass by the HDC.
6/7/18 - Nestor weed-wacked in front of the HDCbuilding.
6/9/18 - Safety cones were placed on well locations in Area B. Nestor A. removed old broken doors from the fire shed. A manhole cover was replaced near the Hospital building after removal last week. Plants were watered by Tony. Our propane grill was brought out of storage.
6/12/18 - Nestor weed-wacked the back areas of the lawn. Tony watered the gardens.
6/14/18 - Nestor weed-wacked the front lawns and also cut all the grass around building. Tony watered the gardens. A grounds clean-up was undertaken: 3 ties moved to behind the N&W caboose, a re-railer was moved to under the tank car, many pallets from 2 areas were located to a pallet pile behind the Guardhouse, 3 imbedded wood blocks were removed from lawn, the arc welder was moved so OSC has clear access to their well, a switch stand and throw was moved to the speeder display, two river buoys were moved to behind the Guardhouse and various switch parts and air hoses were moved inside.
6/19/18 - Nestor weed-wacked along Lee Street and around the entire building. Jeff S. cut grass in Area A between the Buffalo River and the parking lot. Nestor cut the grass beside the Guardhouse and moved two pieces of rail and 4 couplers out of the grass and placed them under the display boxcars.
6/21/18 - Nestor cut the remaining grass in Areas A and B.
6/26/18 - Nestor cut the front lawns of the HDC and also weed-wacked. Tony watered the gardens and took trash to the dumpster. Ed and our electrical contractor surveyed the Guardhouse for an estimate to bring in electrical power. A new, higher utility pole will be needed to replace a shorter pole. All EMT conduit and outlet boxes should be stripped from the building. LED lighting will be installed. Power to our display rail cars was also included in the estimate.
6/28/18 - Nestor cut the lawns between the Don Owens Center and the Hospital Building and Pump House and also weed-wacked. Tony and Erica weeded the front gardens and Erica planted flowers by Archive Building. OSC's Tom Wagner used a brush-hog to cut all the swales in Area A. He also cut along the sidewalks by the Area E parking lot.
6/30/18 - Nestor and Jeff picked up trash along our Elk Street lot. They also cut and weed-wacked all the grass along the sidewalk. Tony watered the gardens.
- HOUSEKEEPING - 6/1/18 - Tony watered the plants and swept the floors.
6/2/18 - Tony watered the plants and did the dishes.
6/5/18 - Tony watered the plants and collected the trash. Barb collected the mail. Don Williams removed a pile of metal scrap from the back-hallway.
6/7/18 - Jeff finished replacing all the stained and missing ceiling tiles in the Bar Room and Meeting Room. He will start on the hallways next. Tony watered the plants and did the dishes. Our contractor cleaned the restrooms and mopped the corridors. Barb met with them to inspect the work and go over contract terms.
6/9/18 - Jeff started replacing all the stained and missing ceiling tiles in the first floor corridor and lobby. Leslie set up and decorated the Meeting Room for a party. Tony washed the dishes.
6/12/18 - Jeff replaced more stained and missing ceiling tiles in the second floor corridor. Tony did the dishes and cleaned surface areas.
6/14/18 - Jeff worked on replacing ceiling tiles. Our contractor cleaned the restrooms and corridors.
6/16/18 - Tony did the dishes, collected trash and watered the gardens. Barb collected the mail and cans/bottles for deposit.
6/19/18 - Tony watered the gardens and plants, did the dishes and collected trash. Ed checked all the rooms for leaks and only found one downstairs near the elevator.
6/21/18 - Tony did the dishes, collected trash and watered the plants. Our contractor cleaned the restrooms and mopped the floors. The SPM crew changed out some exits in the corridor.
6/23/18 - Tony did the dishes and cleaned countertops. Steve K. checked all the upstairs rooms above the ceiling tiles for leak points and found two. Barb vacuumed the carpets and picked up mail.
6/26/18 - Ron organized the Bar Room and Tool Room while Tony did the dishes, watered the plants and cleaned counter tops.
6/28/18 - Our contractor cleaned the restrooms and mopped the corridors. Ron organized the Tool Room and placed all our power tools in the Janitor Closet in the Archive building.
6/30/18 - Ron and Steve cleared out the Bar Room of storage items and coolers were filled. Tony washed the dishes and took the trash to the dumpster. Desk organizers were put in place and stocked with membership items and handouts. Steve also opened up Hospital Building to let it air out with the aid of a fan.
-
"RAILMASTER" PARK TRAIN - 6/1/18 - Bob Snyder performed maintenance on the locomotive.
6/7/18 - Bob removed the gas tank, drained out the old gas and reinstalled the tank. The trailer is ready for Joe to move to Orchard Park.
6/14/18 - Bob checked out the "Railmaster" trailer for its movement to the Orchard Park Depot. Tire pressure was checked, lights and all items secured.
6/16/18 - Joe K. hauled the train to Orchard Park Depot with his truck. Thank you Joe!
-
MECHANICAL - 6/2/18 - Marty and Nestor replaced more worn parts and continued maintenance on the Grove crane.
6/5/18 - Marty and Nestor completed the repairs to the crane and tested it. All that is remaining is topping it off with anti-freeze and hydraulic fluid. Ed ordered a new water pump for the fork-lift and Ron picked up a re-filled propane tank for it.
6/7/18 - Ed picked up the new water pump for the fork-lift and Mike installed it. Mike will refill another propane tank tomorrow.
6/9/18 - Marty and Nestor replaced hydraulic hoses on the Grove crane. Mike installed a new water pump on the fork-lift.
6/12/18 - Marty and Nestor removed the radiator on the Grove crane, flushed it clean and then reinstalled it. New hoses were installed and then they filled it with coolant and checked for leaks. (none)
6/14/18 - Ron picked up another tank of propane. Ed picked up bolts and a belt for the forklift.
6/16/18 - Nestor A. picked up the hydraulic fluid and oil for the Grove crane. Marty L. and Nestor changed the oil filter, refilled the engine with oil and also put in 10 gallons of hydraulic fluid. The engine was started and run for 20 minutes. Next up, the governor will be rebuilt.
6/23/18 - Ron picked up a battery for the backhoe and Mike P. installed it. He also topped off the hydraulic fluid for the bucket. Jeff S. replaced a belt on our lawn tractor, replaced two blades, adjusted the mower deck and reinstalled the side guard.
6/26/18 - Marty & Nestor removed the governor from the Grove crane, cleaned it and began to rebuild it. Jeff S. removed the carburetor and air filter from our lawn tractor, purchased new parts, and rebuild the carburetor.
6/30/18 - Jeff put all the parts together on the lawn tractor and installed a new battery. It now runs great! Nestor and Jeff made adjustments to the Jacobson gang mower and freed up the outer cutters. More grease cartridges are needed.
-
BUILDING #75 - 6/1/18 - Mike P. and his crew continued to remove stored items from the building.
6/2/18 - Mike continued to empty Building #75. Mike's crew carefully moved a glass display case from the building to the D&H boxcar. Joe K. and Ed P. prepared lease documents for the building.
6/3/18 - Mike and his crew cleaned more items out of the building.
6/5/18 - Mike and his crew cleaned more items out of the building.
6/7/18 - Mike and his crew continued to empty Building #75. The building is now 80% empty. Interior demolition of the office area stud walls will start tomorrow.
6/9/18 - Demolition of the interior walls has started. Steve removed remaining Buffalo Color artifacts.
6/12/18 - A 30-yard dumpster was delivered to the front of the building. Mike and his crew demolished over 60 feet of interior walls. 100 concrete blocks were salvaged and delivered to the Guardhouse to do wall repairs.
6/14/18 - Another 50 linear feet of wall was demolished. Over 2000 sq.ft. of ceiling tiles were removed. Three 30-yard dumpsters have been filled. Another pallet of concrete blocks has been saved for the Guardhouse.
6/16/18 - Mike P. and his crew have removed all the interior stud walls. About 100 feet of concrete block walls are to be removed next. Work has started on the removal of air ducts, pipes and obsolete electrical conduit overhead. A third dumpster has been filled.
6/19/18 - Mike and his crew contine to removed more overhead utilities.
6/21/18 - Mike and his crew started removing the interior concrete block walls. Overhead utilities in the south end of the building have been completely removed.
6/23/18 - Mike and his crew continued removing interior concrete block walls. Over 50 linear feet came down and was loaded by our back-hoe into the fifth dumpster. Mike moved 2 more pallets of blocks to behind the Guardhouse.
6/26/18 - Mike and his crew continued removing interior concrete block walls. A "RiverWorks" architect surveyed the building and took measurements and noted structural supports. Ed toured the building with our electrical contractor with a view toward bringing power to the building. An estimate will be prepared. He also estimated the cost of electrifying Buildings #82, #83 and #85.
6/28/18 - Mike and his crew continued removing interior concrete block walls. Mike made a dump run which included old moldy wooden cabinets from the Guardhouse. Mike also ordered up a 5th dumpster for concrete blocks.
6/30/18 - Almost all the interior concrete block walls are removed.
-
BUILDING #82 - 6/2/18 - Nestor replaced a 20-ft missing panel on the west side of the building. Pallet shelving was erected in the building for better storage of materials.
6/5/18 - Mike welded a pair of temporary gates salvaged from Building #75, to the large opening to the building.
-
ARCHIVE BUILDING - 6/2/18 - Mike removed the remaining sink. Steve and Jeff erected more shelving. Steve K. sorted some archives. Jeff S. and Steve polished up some metal signs from the archives.
6/16/18 - Steve K. erected more shelving. Mike P. removed all the trash and debris and placed it in the Building #75 dumpster.
6/30/18 - Steve secured plywood from Building #82 and cut boards for shelving. Ron and Steve organized the Tool Room. A Safety Cabinet was established, labeled and stocked with safety gear: masks, helmets, gloves, & glasses/goggles. All gas containers and lawn maintenance items were moved to the guardhouse. An Electrical Cabinet was established and labeled. All electrical items: bulbs, cords, alarm boxes, fire boxes, light fixtures, wire, etc are now housed in it.
- GUARDHOUSE - 6/3/18 - Nestor, Mike and his crew removed plywood and several tables and placed them in Building #82. The stand-up compressor was placed next to the door for Tom Gould. Building was better organized and much space was freed up.
6/5/18 - Mike removed tables and other artifacts from the building to a trailer. A welder was brought in from Building #75.
6/7/18 - Mike had a welder in to look at welding grates to the windows. The south back door will be welded or bricked up. Ed has called an electrical contractor to get quote on installing power to building.
6/19/18 - Ed spoke with an electrical contractor who will survey building Thursday for bringing power into building.
6/28/18 - Don W., Nestor A. and Jeff S. removed old, broken, moldy wooden cabinets and took them to Building #75 for a run to the dumps. They also loaded 8 rusty, broken metal file cabinets on Don's truck for a trip to the recycling center.
-
ERIE LACKAWANNA BOXCAR - 6/7/18 - Art Toale and Jerry Bower finished erecting the stairs and railing. The steps and platform are now complete.
Thank you Art & Jerry!
6/12/18 - Art and Jerry built a ground platform at the bottom of the stairs. They also surveyed the firehouse shed to estimate materials and costs to build new doors.
- PUMP HOUSE - 6/7/18 - The main feed line has sprung a leak. Ken Vaughn shut off the water. A sign was placed on door "Out of Order". The lock was changed on door to same key as Building #75. Tom Wagner of OSC has been informed.
-
HAMBURG WOODEN RAILCARS - 6/16/18 - Ed P. has secured a bid to shrink-wrap our 1896 NYC Caboose and our 1910 Michigan Central Baggage car prior to their move to the HDC. Joe is awaiting bids to move the cars.
6/23/18 - Caryl Y., Paul M., Don O. and Barb O. took the initiative to cut a path around our cars in Hamburg this afternoon. Caryl gets at least two double hoorahs for his extra hard work with a weed-wacker equipped with a blade. Paul, Don and Caryl used chain saws while Barb got into tight spots with lopping shears. Vegetation will not be a barrier to moving the cars however, track work will be needed from the BSOR mainline switch to the cars. We now need to inventory what's stored in the cars, examine them for the move and do whatever else is needed to get them moved off the Auto Shop property as soon as possible.
- ERIE CABOOSE - 6/21/18 - Ron received the final Eagle Scout Plan for painting the caboose and signed off on approval. Painting will start later this summer.
- LIBRARY - 6/2/18 - Ed and Diane worked on Library projects.
6/5/18 - Ed, Chris, Pat, Mike and Jan worked on projects.
6/9/18 - Diane worked on Library projects.
6/12/18 - Donna, Jim, Pat, Jan, Mike and Chris worked on Library projects.
6/14/18 - Jim and Ed worked on Library projects.
6/16/18 - Jim, Donna, Diane and Ed worked on Library projects. Ed got our recently donated micro fiche machine operating. Ed has also been in contact with City officials about an upcoming Library grant.
6/19/18 - Jim, Donna, Diane, Mike, Pat, Jan, Chris and Ed worked on Library projects. Ed installed new genealogy software.
6/23/18 - Ed, Jim & Donna worked on Library projects. Steve archived all the week's donations.
6/26/18 - Jim, Jan, Chris, Pat, Mike & Donna worked on Library projects.
6/30/18 - Diane worked on Library projects. Peter worked on archives.
|