- BUILDINGS AND GROUNDS - 11/2/15 - Lobby Roof - Mike P. inspected the roof, moved stone and probed for leaks. Located problem areas and purchased supplies to do the repairs.
11/3/15 - Lobby Roof - Mike and his crew removed stone from the roof and placed it in the front loader bucket and placed it near the ballast pile. Roof was power washed and tarred. Jerry and Ron removed stained ceiling tiles from the Church area, cut new ones and replaced them. Grounds - Erica weeded the front gardens and trimmed the bushes.
11/7/15 - Jim Long brought his lawn mowers and cut all lawns around 100 Lee Street. Tony watered plants.
11/10/15 - A contractor installed our new glass door with a mail slot and improved insulation. The old glass was placed in the Hospital Building glass storage area. Mike and his crew patched and tarred several suspected leak points on the main roof.
11/12/15 - Mike Pietrocarlo stopped by to check roof repairs on the Lobby and Church areas. Both were dry.
11/14/15 - Joe was in to turn on the heat and adjust temp controls.
11/16/15 - Dan replaced all the ceiling tiles in the lobby and removed light lenses and cleaned them. Ed vacuumed carpets.
11/18/15 - Dan replaced more stained tiles in the entrance area. He also fastened down the loose flashing on the Pump House that was blown off in the last wind storm.
11/19/15 - Area A - Contractors started to install steel pilings along our shoreline, starting at the DL&W bridge and working their way toward Building #75.
- HOUSEKEEPING - 11/4/15 - Antique "Two Man Track Drill" and a step stool were placed in Archive Building. Striping paint and stencils were placed in the Tool Room. Wall calendar, cash boxes, portable radios, BCK brake club placed in Rm 160. RR association membership plaque hung near bulletin board. Paperwork on desk organized. All box fans were placed in the Kitchen. Trash removed. Trash bags restocked. Shelves organized.
11/7/15 - Barb scrubbed the NKPTHS Archive storage room floor.
11/16/15 - The back hallway entrance was completely cleaned out. A stained ceiling tile in the Bar Room was replaced. Three stained ceiling tiles in the Church were replaced. Ed took home an old Model T car motor to rebuild it for sale. Dishes were washed.
11/19/15 - Ron removed trash, brought in a bag of cans, sold two calendars, cut up stained ceiling tiles, replaced towels in restrooms.
11/21/15 - Trash was removed, 2 bags of cans were secured, poinsettia sale notices were posted, back door was repaired, empty boxes were brought in for Machine Shop parts, Meeting Room was put back in order.
11/24/15 - Erica raked up leaves, potted several plants and mopped the floors. Barb cleaned the restrooms, removed trash, cans & bottles.
11/28/15 - Shelia and Steve started our Christmas decorations.
- BUILDING #82 - 11/3/15 - Dan and Mike Patton disassembled 20 metal shelving units and moved them to the Hospital Building.
11/5/15 - Dan and Mike disassembled another 12 shelving units and moved them to Hospital building.
11/10/15 - Mike and Dan disassembled another 6 steel shelving units.
11/18/15 - Mike and Dan disassembled more 3'x3' shelving.
11/19/15 - Mike and Dan disassembled the remaining 3'x3' shelving and moved it to the Hospital Building.
- ARCHIVE BUILDING - 11/3/15 - NKPTHS ARCHIVES - Barb mopped floors and cleaned wall tiles in the new NKP storage area.
11/4/15 - Tool room was further organized. Trash was removed. New cabinet for paint storage added.
11/5/15 - Chairs for cleaning were placed in Shower Room. Empty boxes were staged for Saturday's machine shop inventory. Diesel engine piston and journal cover were moved to the building.
11/7/15 - ELHS ARCHIVES - The ELHS archivist was in town and met with Ed Patton concerning over 5,000 EL employee records, which will be added to our data base.
11/10/15 - Dan and Mike brought in seven steel cabinets with locking doors for archive storage. These were placed in the shower room.
11/12/15 - A crew of six NKPTHS volunteers lead by John Slater unloaded a truckload of NKP archives and placed them in their new storage space, following a brief ribbon cutting ceremony. We unloaded the Don Daily bequest brought in from Frankfort, Indiana this morning and it is now secured in the NKPTHS new space awaiting sorting and assessment.
11/14/15 - ELHS ARCHIVES - Archivist Joe Schveder and President Mike Connor were in to continue stocking shelves and conduct an inventory.
11/19/15 - ELHS ARCHIVES - The ELHS Archivists requested more space for storage. A room will be provided in the Hospital Building.
11/21/15 - ELHS ARCHIVES - ELHS President Mike Connor visited and discussed a new lease for more space. Mike also brought in two more boxes of Erie Railroad personnel files for BIGS.
11/24/15 - ELHS ARCHIVES - ELHS President Mike Connor and his helper brought in a carload of Erie dispatcher sheets. Jerry, Ron, Peter, Mike, Dan, Mike C and his helper all unloaded this heavy inventory and placed it on shelving in the Hospital Building.
11/24/15 - NKP ARCHIVES - John Slater patched holes in his storage room, painted the patches and put on a new lock.
- MACHINE SHOP -11/17/15 - Ed, Don, George, Rick, Dave and Dan brought five truckloads of donated parts and tools from an inner city machine shop, valued at over $15,000 we will add to our inventories for car repairs. Items were placed in the Guardhouse and Archive Building.
11/19/15 - Ed, Dan, Mike and Mike Pietrocarlo's man and truck hauled a full load to the Guardhouse. Included were a lathe, drill press, wash tanks, tool carts, parts, etc.
11/23/15 - Everyone helped move another load of parts and tools from the machine shop and brought to the Guardhouse. The work was heavy, cold and dirty but our volunteers did a great job. Tomorrow they will be at it again. Thanks to Mike for use of his truck.
11/24/15 - Dan & Mike Patton, along with Mike Pietrocarlo and his two crew loaded two more trucks full of shelving and machine parts. The pallet shelving was put in the Hospital Building and everything else in the Guardhouse.
- HOSPITAL BUILDING - 11/4/15 - Mike and his crew capped the old AC unit after they removed it from roof. Tarred around all entry points. Added reduction piping inside to allow for a 1" water line with faucet so we will have water in the building. Repaired water leaks.
11/5/15 - Mike and his crew finished installing a water outlet in the building. Also prepared a report of recommended remaining work. Disassembled shelving was brought to the building by Dan and Mike.
11/7/15 - Mike and Dan Patton finished painting the first coat in the large archive room.
11/12/15 - Dan and Mike started a second coat of paint in the large archive storage area.
11/16/15 - Mike finished the second coat of paint in the small office. He also blocked off an opening to the roof. Three bags of trash were removed. Also two cubic feet of metal scrap was added to our scrap pile outside the building.
11/19/15 - Ed determined there was no gas line into the building. Mike & Dan moved in 5 assembled 3'x3' shelving units and placed them into the back room for ELHS archive use.
11/21/15 - Mike & Dan repaired back windows, washed down panel walls, foamed in insulation around windows, scrubbed and mopped the floor. They also vacuumed corners and blinds, sanded shelving and painted them and then installed the four shelving units for ELHS archives.
- GUARDHOUSE - 11/5/15 - Mike Pietrocarlo surveyed the roof and made a list of recommended work to stop leaks. A new lock was placed on the door.
11/10/15 - Dan, Mike and Jerry brought in a large steel locking cabinet with doors for tool storage. They also removed 3 scrap lawn mowers.
11/18/15 - Ed moved the forklift to the Guardhouse for tomorrow's move of the lathe and drill press from the machine shop.
- MECHANICAL - 11/5/15 - Jim long mounted a new tire on the compressor with the assistance of Ed on the backhoe.
11/19/15 - Jim Long delivered our reconditioned mower deck for our MTD Tractor. He took the batteries for our mowers for winter storage and will keep them charged. He also put air into all our tired vehicles (welder, mowers, compressors, auto, etc.)
- LIBRARY - 11/3/15 - John, Jim, Donna, Chris and Ed continued data input and cataloguing.
11/5/15 - Ed, Jim, Donna and John continued with library projects.
11/7/15 - Ed, Jim, Donna, Diane, Shelia and John continued with library projects.
11/10/15 - Ed, Jim, Donna, Shelia and John continued with library projects. Historian Mark Goldman visited the Library. The Library was also toured by a potential renter.
11/12/15 - Ed, Jim, Donna and Bob continued with library projects.
11/14/15 - Jim, Donna, Shelia, Diane and John continued with library projects.
11/17/15 - Jim, Donna, John, Chris and Tony worked on Library projects.
11/19/15 - Jim, Donna, Shelia and Tony worked on Erie personnel files.
11/21/15 - Jim, Donna, Shelia, Diane and Tony continued work on Erie personnel files.
11/24/15 - Jim, Donna, Chris Tony, John and Shelia continued work on Erie personnel records.
11/28/15 - Donna, Jim, Chris, John, Tony, Shelia, Steve and Diane worked on various library projects.
|