TrainWeb.org Facebook Page
Midford
S&DJR Crest Somerset & Dorset Joint Railway
Signalling at Midford
S&DJR Crest
Introduction Early Signalling 1892 Doubling Layout Changes Signal Changes Signal Box Ground Frames Block Working Treadles & Track Circuits

Author's Note: I do not yet have all the necessary diagrams or pictures to complete this page. However I thought that it might be of interest in the meantime to publish as much information as is currently available. Hopefully the lack of some of the diagrams or pictures will not make it impossible to understand the context of the historical information about the layout and signalling changes at Midford. Additional historical material and photographs can be found in the article on 'Signalling at Midford S&D' by Mike Arlett in Railway Archive Issue 39 (June 2013).

Introduction

The railway station and signal-box at Midford were situated on the main line of the Somerset & Dorset Joint Railway (S&DJR), on the section from Bath Junction to Evercreech Junction in the county of Somerset which was known historically as the 'Bath Extension'.

Midford station looking up the line in 1957   Midford station looking down the line across the viaduct
Midford looking up the line through the station and down the line across the viaduct

In 1874 the Somerset and Dorset Railway (S&DR) opened its 'Bath Extension' from Evercreech Junction to Bath and a station was provided at Midford. At first the line was single-track throughout with a few passing-places and, according to an undertaking given to the Board of Trade (BoT) by the S&DR on 15-July-1874, the only block post between Bath Junction and Radstock was at Wellow (the next station south of Midford). The S&DR became the S&DJR in 1875 when the line was leased jointly by the Midland Railway (MR) and London & South Western Railway (L&SWR). Click here to read more about early S&DR/S&DJR Signalling and the nature of the original signalling and layout arrangements on the Bath Extension.

With a steady increase in traffic various sections of the Bath Extension were doubled piecemeal, until by 1894 the entire line had been doubled northwards from Templecombe No.2 Junction up to Midford. The last section from Midford into Bath was to become one at the bottle-necks of the S&DJR system, for all Down trains leaving Bath were faced with an immediate climb at 1 in 50 and 1 in 66 for over two miles through Devonshire Tunnel (440 yards) to the north end of Combe Down Tunnel (1829 yards); both tunnels had limited clearance and were very unpleasant to work through (Combe Down being the longest unventilated tunnel in Britain). It was the cost of doubling these tunnels that finally prevented completion of the doubling right through to Bath and although some work was done in preparation for doubling up as far as the approach to the south end of Combe Down Tunnel that scheme was never carried out. This left Midford as a key location at the change from single to double track.

Midford station was a simple affair, a single platform with wooden buildings set on the Up side of the line at a location where it ran on a narrow ledge along the hillside. Northwards the line passed under a minor road by bridge No 17, known as the 'Long Arch' - it was built at such a skew that, at 37 yards, it was more like a short tunnel. Just north of bridge 17 a point, facing to Up trains, led to the two sidings on the Down side which formed the diminutive goods yard. South of the station the line went immediately onto a double track viaduct which carried it across the main road, the Wellow Brook, the Great Western Railway's Limpley Stoke-Camerton-Hallatrow branch and the remains of the Somerset Coal Canal, before passing through a cutting and winding its way on to Wellow and beyond. In the cutting a siding trailed off the Up line; although little used in later years, at one time it saw traffic such as hay shipped out from local farms and explosives unloaded for local collieries.

After the Grouping of the railways of Great Britain in 1923 the S&DJR became a Joint line under the control of the London, Midland & Scottish Railway (LMS) and the Southern Railway (SR), who were the successors to the MR and L&SWR respectively. When the railways were nationalised in 1948 the Joint line came under the control of British Railways (Southern Region) (BR(SR)), but in due course control of the old Bath Extension section passed to British Railways (Western Region) (BR(WR)) until the line closed on 6th March 1966.


Early Signalling

When the Bath Extension was opened the block working on the single-line was by block telegraph without any train staff, and under the terms of the S&DR's 1874 undertaking to the BoT the first block post south of Bath was supposed to be at Wellow. However it is clear from the evidence in the BoT Report on the disaster at Foxcote (near Radstock) in August 1876 that Midford station had been acting as some form of intermediate block post at that time. It is unclear exactly what the original signalling arrangements were at Midford, but it would appear to have included the provision of Distant and Home signals in both directions, worked from a lever-frame probably located in a small wooden hut somewhere on or close to the platform. Even after the Foxcote accident it is clear that this installation continued to function as a block post, as evidenced by references in the S&DJR's Working Timetable Appendix No 7 dated 1-March-1886.

On 3-October-1886 Electric Train Tablet (ETT) working was introduced between Bath and Radstock (using Tyers No 1 instruments), after which Midford became a non-block location within the Bath Single Line Junction - Wellow section. Nevertheless it appears that the signals remained in use at Midford for 'station stop' purposes only. The steep gradient out of Bath necessitated the provision of banking engines on almost all Down freight trains, but assistance was needed only as far as the summit at the north end of Combe Down Tunnel. Special banking arrangements had been in force since 1876 on the Bath Single Line Junction - Midford section involving the use of a 'Bath Bank Staff' and these arrangements continued with the advent of ETT working (click here for further details).

[Note: it is believed that the Bank Staff was brought into use on 22-December-1876 by S&DJR Signal Instruction No 1, but no copy of that Instruction has been sighted yet.]


Part of the 1892 Signal Diagram submitted to the Board of Trade

1892 Doubling of the Line

In 1892 the line from Midford to Wellow was doubled and new signal-boxes (SB) were provided at both locations, the new work being opened on 28th August that year (The National Archives file MT6/598/1). The diagram above is part of a drawing sent to the BoT in connection with the new work - click it to see a larger image of the complete diagram. Midford now became a block-post again and worked ETT to Bath Single Line Junction (presumably using the Tyers No 1 instrument relocated from Wellow) and Absolute Block to Wellow using S&DJR 'block telegraph' instruments. The 'Bath Bank Staff' arrangements continued, but with the bank engine staff now being interlocked with the ETT instrument at Bath Single Line Junction SB.

[Note: the diagram shown above is one of a number of drawings submitted to the BoT for various S&DJR line-doubling schemes in the 1890s which were not in the relevant TNA MT6 files when research was done. The originals were found in BR(WR) records some years and copies are now in the WCRA collection. In the absence of any evidence to the contrary, it is assumed in each case that the work was implemented as drawn.]

The new SB at Midford was situated on the Up side of the line between the south end of the platform and the viaduct, and it was built to the same S&DJR TYPE 2 style as various other replacement SBs on the Bath Extension - a gable-roofed timber superstructure decorated with a distinctive style of wavy valencing on a stone base, but with a brick rear wall and chimney stack. The new double track extended right across the viaduct, with a crossover (points 9) about half way along, and the Up Inner Home signal (14) was on a wooden post bolted onto the outside of the viaduct. One feature of the early signalling at many S&DJR double-line locations was the provision of a subsidiary arm under the stop signal next in rear of the section signal; in common with other S&DJR subsidiary arms, this would have been a full-size arm with a ring and here at Midford signal 3PUSH was an example. Lever 3 was a 'push-pull' lever, which normally stood in the mid-stroke position; the signalman could pull the lever back to operate one signal, or push the lever forward to operate a different signal.

Midford signal diagram 1892   Midford signal diagram circa-1912
Midford Signal Diagram 1892 Midford Signal Diagram circa-1912
Click diagram for larger image Click diagram for larger image

It is believed that all the original main running signals provided in 1892 were lower-quadrant (LQ) arms on wooden posts. At some date circa-1900 three additions were made to the signalling at Midford (see the circa-1912 diagram above). Lever 12 was brought into use to control a subsidiary ringed arm located beneath the Up Outer Home (15), although its function is a little confusing; described as a 'Shunt By' arm in the lever-frame locking table, it was often referenced in notices as a 'Calling On' arm and in BR days it was marked on SB diagrams as a 'Warning' arm. In later years it seems to have been used to draw trains forward to shunt the Up Siding, either to put a light engine out of the way or to drop off a vehicle with a hot-box. As it locked signals 2 and 3 it could not be used for such moves when a Down train had been signalled.

Lever 5 was brought into use (probably at the same time) as a 'push-pull' lever. The 5PUSH function operated a new ground signal, which was located on the outside of the Down line just south of the facing points 8 and controlled movements from the Down line back onto the single-line. The 5PULL function worked what was perhaps the most notable feature of the installation at Midford, namely the 'wrong-road' signal situated on the platform. This was probably the first signal at Midford to be installed on a lattice metal post rather than a wooden post. Eventually there were two such signals at Midford, as on 11-June-1929 (S&DJR Signal Instruction 293) a 'repeater' arm for 5PULL (also of the 'wrong-road' type) was provided under the Down Home signal (2) (which in fact stood on top of the 'Long Arch' overbridge). These signals were used on the occasions when an Up Goods failed to make the climb up the 1-in-50/1-in-100 gradient to Combe Down tunnel. The driver would telephone back to Midford (using a telephone provided for that purpose close to the southern end of Combe Down tunnel) and receive the signalman's permission to reverse back out of the section. On return to Midford the train might be shunted on to the Down line, but some times the traffic pattern required that it be put onto the Up line while it awaited an assisting engine or tried to build up a good head of steam; it was for these moves onto the Up line that signal 5PULL was used.

[Note: there is no known record of any form of 'Limit of Shunt' indicator being provided on the Up line to limit any wrong-direction movements back towards the Up Outer Home (and possibly beyond). One may speculate that perhaps the Sykes interlocking provided in connection with the block working to Wellow (see below) was considered sufficient to prevent any possible conflict with an Up train.]


Layout Alterations

In the original 1892 layout the only provision for goods traffic was a single siding trailing off the Up line south of the viaduct. This siding was controlled by a ground-frame (GF), housed in a small wooden hut and bolt-locked by lever 11 in the signal-box. However in December 1894 a small goods yard with two sidings was opened to the north of the station. This yard was situated on the Down side of the line immediately on the Bath side of the 'Long Arch' overbridge and was accessed by a point in the single-line facing to Up trains. This connection was controlled by its own GF, situated in a small wooden hut on the Up side of the line, and locked by the single-line tablet. This new GF became known as GF 'A', while the original one at the Up Siding became GF 'B'. Both GFs also worked ground signals controlling movements into and out of their respective sidings. More details about both GFs can be found below.

The crossover (points 9) on the viaduct would seem to have been of little use and eventually was removed (together with the associated ground signals 10PUSH and 10PULL), this alteration being authorised by S&DJR Officers' Minute 7013 dated 26-April-1918. As part of a general programme to improve speed restrictions on the line, on 9-April-1933 the facing points (8) were re-sited much further south along the viaduct, thereby raising the speed restriction for Up trains from 20 mph to 40 mph. The relocated points were now 98 yards south of the signal-box, with ground signal 5PUSH being relocated between the Up and Down lines 206 yards from the SB (S&DJR Signal Instruction 330). This alteration also involved a further southwards relocation of the Up Inner Home bracket signal (14) to a position 206 yards from the SB, and the Down Advanced Starting signal (4) to 470 yards, both the changes taking place the previous weekend on 2-April-1933.

After 1933 there were no further changes to the general layout at Midford until about 1959/60, when the Up Siding and GF 'B' were taken out of use. It would appear that the actual siding was taken out of use first in June 1959 (BR(SR) Weekly Notice P/EW21) and then in 1960 the siding and GF 'B' were taken out of use (permanently) on 28th February (BR(SR) Weekly Notice P/EW9), after which they were removed, although confusingly a 1960s BR(WR) locking sketch copy was annotated that the GF was abolished in December 1959. The goods yard and GF 'A' were closed in 1963/64 and recovered on 29-June-1964.

Various S&DJR WTT Appendix instructions for Midford
1905 WTT Appendix instructions   1914 WTT Appendix instructions   1933 WTT Appendix instructions
1905 Edition 1914 Edition 1933 Edition
Click thumbnails for larger images

Signal Alterations

Signal 3PUSH was abolished on 15-April-1913 (S&DJR Signal Instruction 237), after which lever 3 became a 'normal' lever working the Down Starting signal only. By 1922 the original Up Inner Home signal (14) had been replaced by a right-hand lattice bracket sited just south of the viaduct. This signal was relocated again further southwards to a position 206 yards from the SB as part of the 1933 layout alterations, and the Down Advanced Starting signal (4) was moved out also to 470 yards, both these changes taking place on 2-April-1933 (S&DJR Signal Instruction 330). At the same time ground signal 5PUSH was relocated between the Up and Down lines 206 yards from the SB. Then on 21-May-1933 both ground signals at GF 'B' were removed (S&DJR Signal Instruction 336).

The Up Distant signal (16) was lowered by 12' on 2-September-1924 and two days later the Down Distant signal (1) was lowered by 6' (both S&DJR Signal Instruction 276). On 29-July-1936 the Down Starting signal (3) was demolished as a result of an accident with a runaway train, but evidence would suggest that the original post was re-erected in a shortened form. It is probable that it was at that time that the signal was fitted with an upper-quadrant (UQ) arm and this may have been the first UQ arm to be provided at Midford; it is presumed that all subsequent signal replacements done at Midford also used UQ arms until 1960. The Down Distant was replaced by a new signal 15' high on 22-March-1942 and also on the same date a 25' high replacement was provided for the Up Starting (13) (both S&DJR Signal Instruction 389).

Midford Up Outer Home signal 15 & 'Warning' signal 12Further signal alterations took place on 25-July-1948, when the Up Outer Home signal 15 and subsidiary 'Shunt By' arm 12 were replaced by new signals on a new 20' post 81 yards further away from the SB (see picture). Signal 12 was provided in a new form, becoming a small horizontally-striped arm with an adjacent indicator box on the signal post, and was described now as a 'Warning' signal. [Note also in the picture the 'Rule 55 exempt' white diamond sign, with the large black 'T' on its face to denote that a telephone to the signal-box was provided in the white cabinet with the black-and-white striped plate in the foreground.] On the same day the Up Distant signal was replaced by a new signal 12' high located 306 yards further away from the SB and now 1000 yards away from the re-located Up Outer Home. Subsequently however signal 12 was removed altogether on 28-February-1960 with the closure of the Up Siding (at which time it was still described as a 'Calling On' arm in the abolition Weekly Notice P/EW9), although confusingly a 1960s BR(WR) locking sketch copy was annotated that the signal was abolished in December 1959.

By 1955 the signals were as much a variety as elsewhere on the S&DJR. Some were on lattice posts, but 1 and 16 were on SR-type rail-built posts with UQ arms, whilst 3 and 4 were both wooden posts; 3 carried a UQ arm, but 4 was a tall post with a LQ arm. Signals 13 and 15 also had UQ arms, but the remaining arms (2, 5PULL, 14) were all LQ. GF 'A' still retained its Stevens 'flap' ground signals for moves into and out of the goods yard, whilst 5PUSH was by now a standard Westinghouse 'half disc'. (The one type of S&DJR signal not represented at Midford was that which used the S&D's own pattern of rail-built post, as opposed to the design used later by the SR.) Curiously, whilst signal 1 had a rail-built post, signals 15+12 had a lattice post, yet both had been renewed on the same date - no doubt the signal engineers were continuing to re-use equipment where suitable.

The ground signals at GF 'A' were still in place in May 1955, but had been removed by June 1958; the access point for the goods yard was renewed in early 1956 and it is considered probable that the associated ground signals were removed at the same time. On 11-September-1960 both signals 3 and 4 were replaced, each by a standard BR(WR) LQ arm on a tubular steel post. Because the new signal 4 was much lower than the old one its light could no longer be seen easily by the signalman, so a lamp repeater was provided for it in the SB (there was an arm repeater already). Apart from a solitary example at Masbury, these were the only other such BR(WR) signals known to have existed on the S&DJR until one was installed at Highbridge in March 1966.


Block Working

Bath-Midford fibre tablet No 6 patternAs explained above, when the Bath Extension was opened in 1874 the station at Midford appears to have worked as some form of intermediate block-post in the single-line section from Bath Junction to Wellow, controlled by block telegraph without any train staff. However this arrangement ceased on 3-October-1886 when ETT working (using Tyers No 1 instruments) was introduced on the Bath Single Line Junction - Wellow section. When the line to Wellow was doubled in 1892 Midford became a block-post again, working ETT to Bath Single Line Junction and Absolute Block to Wellow (using S&DJR 'block telegraph' instruments); it is presumed that the ETT working used the Tyers No 1 instrument relocated from Wellow. The 'Bath Bank Staff' arrangements continued in use at Bath Single Line Junction, but effectively Midford had no part in its operation. In 1912 it was decided to replace the original ETT equipment (Tyers No 1) with a more modern version; this is assumed to have been Tyers No 6, as that pattern was in use already elsewhere on the S&DJR and was certainly the type which existed at Midford in later years. Although there is evidence that BR(WR) did consider replacing ETT by Electric Key Token on that section, it remained with Tyers No 6 ETT until the line closed and one of the tablets is shown here.

'Tablet Out' Releases. The removal of a tablet from the ETT 6 instrument at Midford for an Up train released an electric lock on lever 13, so that the signalman could clear the Up Starting signal for a train to proceed to Bath Junction. However there is no known evidence that a 'one pull only' restriction was included in the relevant electrical locking (click here for more information about 'tablet out releases' on the S&DJR). The 1948 Electrical Locking table also records that 'tablet out' releases from Bath Junction was required to release electric locks on levers 5PUSH (but not 5PULL) and 14, because any movements past those signals would occupy the single-line even if not proceeding past the Up Starting. Although not specifically annotated as such on the signal diagram (as was usually the case in later years), the relevant electrical wiring diagram would suggest that the locks on 5PUSH and 14 required only that the signalman should turn the commutator of his ETT 6 instrument to the left upon getting a 'release' from Bath Junction without needing to withdraw an actual tablet.

Sykes Instrument. Signal 5PULL provided for movements from the single-line back onto the Up Line. Such 'wrong line' moves added to the complications of the block working to Wellow, as obviously they could not be made if an Up train had been accepted already from Wellow. To control this possible conflict, in addition to the normal three-position 'block telegraph' instrument for the section to Wellow, a Sykes 'plunger lock' instrument was provided at Midford and this was fitted with a Sykes 'point & plunger lock' (P&P). In order to give 'Line Clear' to Wellow it was necessary first for the signalman at Midford to place (or maintain) the P&P lock handle in the right-hand position and then plunge on the Sykes instrument to release an electric lock on the pegging handle of the three-position block telegraph instrument. (The operation of the plunger also released the electric lock on the lever (6) in Wellow signal-box for its Up Advanced Starting signal.) The Sykes instrument was locked then until 15 (or 12) and 13 had been pulled and replaced, thereby proving that the Up train had arrived from Wellow, passed through Midford and was on its way to Bath Junction.

When the P&P lock handle was in the right-hand position it locked levers 5PULL and 11 to ensure that - once an Up train had been accepted from Wellow - no shunting movements or use of the Up Siding points could foul the 'clearing point' in advance of the Up Outer Home (15). In order to use signal 5PULL or pull lever 11 to unlock GF 'B' then - provided that the Sykes plunger lock instrument was in its normal state - the signalman had to move the P&P lock handle to the left-hand position, thereby locking the plunger in the Sykes instrument so that it could not be used to accept an Up train from Wellow. If 5PULL was used then the Sykes plunger remained locked until lever 5 been put back to its normal mid-way position and lever 13 (the Up Starting) had been pulled and then replaced, thereby proving that the train which had been shunted back onto the Up line had now gone forward again beyond the 'clearing point' for acceptance of an Up train from Wellow.

[Note: despite the use of similar-looking Sykes instruments, this was not a example of Sykes 'Lock & Block' block working. It is probable, but not proven, that the Sykes equipment was provided at the same time as the addition of signal 5PULL.]


Treadles and Track Circuits

A number of treadles (labelled 'A', 'B' and 'C') were provided at Midford in connection with the block and signal interlocking. There was also a treadle 'E' provided on the Up line a short distance in the rear of the Up Outer Home (15), which sounded a warning buzzer in the signal-box and operated a 'Train Waiting' indicator on the instrument shelf until such time as the signalman cleared signal 15 or 12. About 1923 a track circuit 'A' was installed on the Down line stretching south for 1000 yards from close to ground signal 5PUSH. This track circuit extended sufficiently far beyond the Down Advanced Starting (4) to enable the signalman, who could not see far beyond that signal because of the curvature of the cutting, to know when the tail end of a Down train had cleared the end of a stretch of 1-in-60 uphill gradient.

On 4-April-1933 (S&DJR Signal Instruction 331) signal 15 was fitted with a 'diamond sign'. This indicated to the driver of any train detained at that signal that he did not need to obey the section of Rule 55 which required the fireman to go to the signal-box, as the 'Train Waiting' indicator operated by treadle 'E' would warn the signalman of the presence of the train. [Curiously no diamond sign was provided on signal 4 despite the existence of track-circuit 'A'.] In March 1952 a second track circuit 'B' was installed through the facing points 8, extending from signal 3 towards signals 14 and 5PUSH, where it abutted to track circuit 'A'; it was probably at the same time that the 'Last Vehicle' treadle 'B' was removed.

Midford signal diagram circa-1955
Midford Signal Diagram circa-1955
Click diagram for larger image

Signal Box

The 1892 SB at Midford was originally a conventional S&DJR TYPE 2 style, with a gable-roofed timber superstructure decorated with a distinctive style of wavy valencing on a stone base, but with a brick rear wall and chimney stack. However its appearance was altered rather dramatically as the result of an accident which occurred on 29-July-1936; described in detail in "Red for Danger" [1] (which quotes an incorrect date), it was rather humourous overall although obviously it could have had more serious consequences. A locomotive shunting at Writhlington (north of Radstock) was allowed inadvertently to run away crew-less on the Up line, propelling eight empty wagons. On reaching Midford the leading wagon became derailed on points 8, which were still bolted for the Down line. At 10:06am (by the signal-box clock) this truck smashed into the base of the signal-box, knocking a large hole in the wall and shifting the lever-frame, before ending up on the platform. As a result of this accident the SB was rebuilt with a flat roof, which gave it a distinctive look, though exactly why it was given a flat roof is uncertain - possibly simply as a matter of expediency. Contemporary reports mention the dispatch of a temporary box from London, but nothing more is known about this, and the damaged box was rebuilt by Hayes & Sons of Bristol. The rebuilt box can be seen in the photographs above in the Introduction to this page. The signal-box was closed with the line on 6-March-1966.

[Note: the Ministry of Transport's Accident Report can be found in TNA file RAIL1053/122/1. Currently there is a lack of reliable information about the operating arrangements for the period between the accident and the eventual re-opening of the SB at an unknown date, so research continues into this aspect of the history of Midford's signalling.]

A view inside Midford signal-box in 1957Interior. This photograph (click for larger image) shows the interior of the rebuilt signal-box on 23-May-1957 with a variety of equipment, although a general L&SWR/SR air prevailed. The 16-lever frame was of the Stevens direct tappet pattern with levers at 4.1/8" centres; the 'push-pull' lever 5 can be seen in its mid-way position and lever 8 is reversed. All the levers still had the distinctive L&SWR style of rectangular brass lever description plates, except for the spare levers 6, 9 and 10 (painted white); however after levers 11 and 12 were taken out of use in 1959/60 their plates were replaced by the BR(WR) rectangular type with 'Traffolyte' face-plates fixed near the tops of the levers (as can be seen in the circa-1965/66 colour images below).

The Tyers No 6 ETT instrument stood on top of a cupboard in the front left-hand corner, with its 'foot plunger' set in the floor in front of the cupboard. Visible by the front corner of the cupboard is an iron ring handle set into the floor, which was pulled vertically to operate a wire which caused the arm of the Whitaker 'pick up' apparatus (positioned on the Down side of the line) to turn through 90 degrees ready to receive a pouch from a passing locomotive. Some of the Whitaker pouches can be seen hanging on the wall to the left of the cupboard, whilst hanging above them at the top of the window are a few of the larger pouches used for hand exchanges.

Instrument Shelf. On the top of the instrument shelf above the lever-frame, working from left to right, there were the following items:-

Along the front of the shelf there were various signal arm or lamp repeaters which showed whether the signal arm was in the 'on' or 'off' position, or whether its lamp was alight or not. There were also some circular plungers, which operated electric locks on some of the levers in conjunction with the track circuits and other controls; most of the plungers were in brass cases, but there were also two bakelite examples. Working from left to right the equipment was as follows:-

Levers 1 - 8 Levers 9 - 16
  • Lamp repeater for 1 (Down Distant)
  • Arm repeater for 1 (Down Distant)
  • Arm repeater for 2 (Down Home)
  • Release plunger for lever 3
  • Arm repeater for 4 (Down Advanced Starting)
  • Release plunger for lever 5
  • Arm repeater for 5PULL Repeater arm (at the Down Home)
  • Release plunger for lever 7
  • Release plunger for lever 8
  • Two Sykes release key-holes (emergency releases for the two Sykes instruments)
  • Arm repeater for 12 (Shunt By Up Outer Home)
  • Release plunger for lever 13
  • Release plunger for lever 14
  • Arm repeater for 15 (Up Outer Home)
  • Arm repeater for 16 (Up Distant)
  • 'Train Waiting' indicator (operated by Treadle 'E')
  • Lamp repeater for 12,15,16 (three lamps grouped on one repeater)

[Note: there is circumstantial evidence to suggest that fewer repeaters were provided in earlier days and their style would have changed over the years. A partial diagram copy dated 2-May-1933 lists no lamp repeaters and arm repeaters only for signal 4 and the 5PULL repeater arm. A circa-1923 drawing suggests that the original indicator for TC 'A' was a rectangular box which sat on top of the shelf near the left-hand end. The indicator for TC 'B' would not have existed before 1952.]

There was also a small brass push-button recessed into the top of the shelf front just in front of the Wellow block instrument, between the plungers for levers 7 and 8; although its purpose is unknown, it is probable that it was an 'economiser plunger' to operate the electric lock on the block instrument's commutator handle once the signalman had plunged on the Sykes 'plunger lock' instrument. Also visible in the photograph are a pair of Sykes release keys hung on a hook between the two keyholes - handy for a quick release! Note the large suspension-style pressurised oil lamp with the 'lifeboat' pattern fuel container and enamelled reflector, which provided an even spread of mellow light; it was one of two different patterns of Tilley lamps which remained the method of illumination inside the box until the latter years before closure.

Inside Midford signal-box circa-1965/66
Colour view inside Midford SB circa-1965/6 left-hand end   Colour view inside Midford SB circa-1965/6 right-hand end
Click either photograph for a larger image

The arm repeater for signal 12 was removed after that signal had been abolished on 28-February-1960. Later that year a lamp repeater was added for the replacement Down Advanced Starting signal (4); this was a wooden-cased BR(WR)-style indicator installed on the top of the instrument shelf between the Wellow block-bell and Block Telegraph instrument. At some unknown date a small round (bakelite?) toggle switch was fitted to the front of the instrument shelf above and between the arm repeater for signal 16 and the 'Train Waiting' indicator; its purpose is unknown, but it is possible that it was provided to enable the signalman to cancel the warning buzzer which worked in conjunction with the 'Train Waiting' indicator. Both the BR(WR) lamp repeater and the round toggle switch can be seen in the circa-1965/66 colour images above. Also visible behind the frame under the windows are three large ratchet wheels (painted variously yellow or red as appropriate for their signals) used to adjust the wires connecting to signals 1, 15 and 16.

Signal Diagram. Above the instrument shelf was hung a framed copy of the signal-box diagram. In early BR(SR) days this would have been a copy of diagram No 191 complete with the Mechanical and Electrical locking table details, as seen here; this diagram would have been modified in 1952 when treadle 'B' was replaced by track-circuit 'B' and part of it can be seen in the 1957 photograph above. At a later date, apparently in December 1959, BR(WR) produced a new version of the diagram (numbered S435) to their own style without the locking tables; this diagram would have been modified early in 1960 after abolition of signal 12, the Up Siding and its GF 'B'. The post-1959 version can be seen here and in the circa-1965/66 colour images above. Click here for more general information about S&DJR signal diagrams and their identification numbers.

Mdford SB diagram BR(SR) version circa-1948   Midford 'dog chart' circa-1945   Midford SB diagram BR(WR)version circa-1960
BR(SR) SB diagram No 191 circa-1948   Mechanical Locking 'dog-chart' circa-1945   BR(WR) SB diagram No S435 circa-1960
Click any drawing for a larger image

Ground Frames

For most of the period from 1892 to 1966 there were two separate ground-frames at Midford in addition to the signal-box. Although various details about these GFs have been given elsewhere in this page, this section summarises all the relevant information together for clarity and ease of reference. See below for more information about the naming of the Midford GFs or click here for more general information about S&DJR GF diagrams and their identification numbers.

Midford GF 'B' diagram 1948GF 'B'. The first GF was brought into use in August 1892 as part of the new installation for the doubling of the line to Wellow and it controlled the new Up Siding just south of the viaduct. It comprised a 3-lever ground-level frame, almost certainly of the Stevens 'knee' type with levers at 4.5/8" centres, housed in a small ground-level wooden hut (which was probably a Stevens design). Lever 1 was the 'release' lever, lever 2 worked the trailing point and associated trap-point, and lever 3 was a 'push-pull' lever working ground signals for movements into (3PULL) or out of (3PUSH) the siding. Lever 1 was bolted mechanically by a rod run from lever 11 in the SB; it is not known if the lock mechanism was some form of 'midway lock' between the SB and the GF or actually at the GF itself, which was recorded at 283 yards from the SB centre. Originally the locking-table for the GF was included in the main SB diagram but in later years there was a separate diagram and locking-table for the GF (No 191A). On 21-May-1933 both ground signals were abolished (S&DJR Signal Instruction 336) and lever 3 became a spare; the simplified installation is shown in a 1948 copy of Diagram 191A (click for larger image).

GF 'A'. The second GF was provided in December 1894 to control the access to the new Down Sidings goods yard which had been opened just north of the 'Long Arch' bridge. This GF also was housed in a small wooden hut similar to that of the other GF and contained a 3-lever 'knee' frame with levers at 4.5/8" centres. Lever 1 was effectively the 'release' lever, but its main purpose was to control the FPL on the facing point in the main line and also a bolt on the boundary gate across the siding entrance; lever 2 worked the facing point and associated trap-point, and lever 3 was a 'push-pull' lever working ground signals for movements into (3PULL) or out of (3PUSH) the siding. Lever 1 was released by a lock operated by insertion of the one of the electric train tablets for the single-line section; that lock would have been altered later when the ETT equipment for the section was changed from Tyer's No 1 to Tyer's No 6 instruments, as the No 6 tablets were smaller than the No 1 tablets. This installation also had its own diagram and locking-table (No 192) and a 1948 copy is shown here (click for larger image).

Midford GF 'A' dog-chart circa-1945   Midford GF 'A' diagram 1948   Midford GF 'A' dog-chart 1957
Mechanical Locking 'dog-chart' circa-1945   BR(SR) GF diagram No 192 circa-1948   Mechanical Locking 'dog-chart' 1957
Click any drawing for a larger image

In 1956 the points worked from GF 'A' were renewed and there is circumstantial evidence that it was at that time that both the ground-signals worked from GF 'A' were abolished; certainly photographic evidence shows that they disappeared sometime between March 1955 and June 1958. (In the absence of more information, one may speculate that only the facing point in the main line was replaced, as it seems unlikely that the trap-point would have had suffered enough wear-and-tear to need replacement at the same time.) A comparison between a 1945 SR version of the 'dog chart' and a later 1957 BR(WR) version (both shown above) reveals some interesting differences. Firstly, whilst the former recorded levers at 4.5/8" centres (as might be expected), the latter quoted 5"; if one assumes that the frame was not replaced - in which case surely the WR would have used one of their own design - then probably that is simply an error. Secondly, and much more importantly, it is clear from the 1957 version that the locking had been altered and also the functions of some of the levers.

[Note: the SR dog-chart is drawn from the perspective of the GF operator, so lever 1 is to his left and the tappets move towards him when the levers are pulled. In contrast, the WR dog-chart is drawn from the perspective of a locking-fitter working at the rear of the frame, so lever 1 is to his right and the tappets move away from him when the levers are reversed.]

Lever 1 remained as the FPL Lever, but now it locked lever 2 (the points) both ways, having previously only locked it normal. (In similar older installations the FPL did not bolt the point in the reverse position where there were no passenger movements into a siding.) The reason for this change is not known, but it may have been done to provide surety that the point was correctly in the reverse position when shunting into the siding, as there was no longer any ground signal to 'detect' the point. As it was now possible to replace lever 1 to normal when the points were set for the siding, that would allowed the tablet to have been removed for its lock with the points set incorrectly; consequently with the (assumed) abolition of both ground signals lever 3 had been re-purposed to serve as the 'release' lever for the GF and the tablet lock now interlocked with lever 3 instead of lever 1. Photographic evidence shows that the gate remained bolted from the GF, but one must assume that the gate bolt function had been transferred from lever 1 to lever 3; if the gate bolt had remained on lever 1, then the gate would have been bolted across the siding every time the points were locked in the reverse position, which clearly would have been impractical. Unfortunately no post-1956 version of the signal diagram for GF 'A' has come to light yet to confirm the foregoing analysis of the probable revised installation.

Closures. In 1959/60 the Up Siding and GF 'B' were taken out of use. It would appear that the actual siding was taken out of use first in June 1959 (BR(SR) Weekly Notice P/EW21) and then in 1960 the siding and GF 'B' were taken out of use (permanently) on 28th February (BR(SR) Weekly Notice P/EW9), after which they were removed, although confusingly a 1960s BR(WR) locking sketch copy was annotated that the GF was abolished in December 1959. The goods yard and GF 'A' were closed in 1963/64 and recovered on 29-June-1964.

Names. It is probable that in 1892 the original GF was known simply as 'Ground Frame', which was the usual practice where there was only one GF within the 'station limits' of a SB, and certainly it was labelled as such on the SB diagram. However once the 1894 GF was opened it is unclear what official names were used by the S&DJR to identify the two ground frames, especially as the 1894 GF was not shown on any known versions of the Midford SB diagram (probably because it was outside of 'station limits' and not under the direct control of the signalman). In BR days the names 'Midford A' and 'Midford B' (for the 1894 Down Sidings and 1892 Up Siding GFs respectively) were displayed on nameplates on the GF huts and there is circumstantial evidence that these names were adopted in early 1948. For clarity and consistency the BR names are used in RailWest.


Postscript...

In the years after closure almost everything was demolished at the station site and very little remains now except the platform and the viaduct. In the former goods yard the concrete base for the yard crane still exists and as late as 2021 it was still just possible to see the location once occupied by GF 'A', but the site of GF 'B' has disappeared and the former Up Siding area has been buried under rubble. A rummage in the undergrowth in various locations will reveal the remaining stumps of some of the old signal posts. In recent years the New Somerset & Dorset Railway group have purchased the station site, the platform area has been cleared and some information display boards have been erected. A public footpath and cycle-track now exist on the former track-bed.

In the 1980s the Somerset & Dorset Railway Trust recreated (within the limitations of available space and equipment) a representation of the interior of Midford signal-box at their Museum at Washford station on the West Somerset Railway. Sadly the Trust had to vacate Washord station in 2021, at which time the display was dismantled and the equipment put into storage, but the images below provide links to a series of colour pictures showing various parts of that display. Although the display did contain a few small items of S&DJR origin, most of the equipment consisted of items of the appropriate type obtained from a variety of other sources.

Click any picture for a larger image
Tyers No6 Electric Train Tablet instrument to control the single-line section to Bath Junction   S&DJR Block Telegraph instrument, with SRly upper indicator, to control the double-line section to Wellow   The right-hand end of the lever-frame showing the brass description plates for the Up line signals   Sykes indicator for the electric lock on the Up Starting signal No 13   Sykes 'plunger' block instrument for the Up line from Wellow
Tyers No 6
Tablet Instrument
S&DJR Block Telegraph
Instrument
Part of the lever-frame Indicator Lock
Sykes Instrument
Plunger Lock
Sykes Instrument

© CJL Osment 2007-23
Thanks to Steve Ehrlicher and Peter Kay for material from The National Archives, to Mike Arlett for personal reminiscences and additional archive material, also the late Harry Wiltshire and Ivo Peters.
Midford signal-box exterior and B&W interior photographs © Ian Scrimgeour courtesy Signalling Record Society, interior colour photographs © Nick McCamley, all other photographs and drawings WCRA collection.


References

Introduction Introduction Early Signalling 1892 Doubling Layout Changes Signal Changes Signal Box Ground Frames Block Working Treadles & Track Circuits