WORK REPORTS

28 December 2022

('Click' on Photos to 'Enlarge')


24 December 2022    Crew: KentS, GerryG, DanielS & GaryM

Barrel
DanielS continued work on the shed on the east side of the Mechanical Transfer.

Salida
GaryM connected feeders to the DG rails on each side of DG switch #17.

Extras

  • KentS continued tests on the WiFi WFD-30.

  • 21 December 2022    Crew: KentS, TomG, DanielS & GaryM

    Barrel
    DanielS worked on the shed on the east side of the Mechanical Transfer.

    Salida
    TomG replaced DG Switch #17, the old one was slightly long between the throwbar and frog. He also discovered the three rails on both ends of the switch lacked feeders. GaryM worked on DG Switch #34 on the east end of the NG yard. A toad that was long, caused problems for K-36 #480, and was shortened, plus some tight spots in the switch were removed. Most of the yard's DG and NG switches have been tested by #480 in both directions, with the exception of the switches on the shop ladder by DG switch #17.

    Extras

  • KentS tested a WFD-30 WiFi device connected to the NCE DCC that allows your Android/Apple phone or iPad to act as a throttle, while still allowing NCE throttles.
      

  • 14 December 2022    Crew: KentS, GrantC, DanielS & GaryM

    Barrel
    DanielS built the curved dumper rails on the Mechanical Transfer mock-up.

    Salida
    TomG soldered the loose point rail on the west switch of the #3 crossover. TomG also worked on DG Switches #2, #2A and #4 and got them operational. GaryM soldered a loose feeder and improved the transition rails from DG Switch #20 to the SG TT arrival lead. GaryM began testing K-36 #480 east facing on all the switches.


    10 December 2022    Crew: KentS, GrantC, DanielS, StuJ & GaryM

    Parkdale
    StuJ brought out his scratchbuilt depot to replace the stand-in depot.

    Salida
    GaryM continued Test #1 with K-36 #480 (running switch legs, facing west). Transfer Yard DG Switch #4 to the ice-house NG tracks has some major issues, could not negotiate that switch at all.
      

    Barrel
    DanielS continued working on the Mechanical Transfer mock-up.

    Cimarron
    StuJ added a platform to the depot.

    Extras

  • StuJ brought out some sample pine trees and bushes for consideration.

  • 7 December 2022    Crew: KentS, DanielS & GaryM

    Gorge
    Other DanielS making progress on the water pipeline.
      

    Barrel
    DanielS continues building the Mechanical Transfer mock-up.
            

    Salida
    GaryM continued Test #1 with K-36 #480 (running switch legs, facing west). Switch #23 from the Coaling Tower to the Turntable was tight, and corrected. Still having a problem negotiating to the track transition to the 4 rail tracks. The sandhouse foundation is too close to the track, and will have to be relocated back. DG Switch #16 had some tight spots which were filed out; however, it was noticed that this switch was built with an "S" in the diverging track, and will be necessary to replace with a new switch. This switch goes into the car shops. DG switch #13 going to the RIP tracks had some tight spots which were filed out.
            

    Extras

  • KentS replaced the burnt out transformer for a new throttle to the layout test track.
      

  • 3 December 2022    Crew: DanielS & GaryM

    Salida
    GaryM continued Test #1 with K-36 #480 (running switch legs, facing west). West switch of main crossover #3 Shinohara will need to be replaced. The point rail came loose from the joint, it might be possible to fix but doubtful.
      

    Barrel
    DanielS adds mounting bases for dumper rail on concrete abutments.
      

    Extras

  • DustyT used his sign template, rebent the sign, and re-painted!
               
            

  • 26 November 2022    Crew: DanielS

    Barrel
    DanielS works on pads and concrete abutments for "growing" mock-up.
      


    19 November 2022    Crew:

    Barrel
    DustyT's friend's 3D printed barrel assembly.
      


    16 November 2022    Crew: DanielS & GaryM

    Barrel
    DanielS laying out his Mechanical Transfer mock-up. The tower is made of cardboard from a cereal box!
         


    12 November 2022    Crew: GaryM, KentS, GrantC & DustyT

    Salida
    GaryM continued Test #1 with K-36 #480 (running switch legs, facing west). DG Switches #2, #2A require resoldering of outside stock rail to remove tight spots on NG and SG rails. All other DG switches south of Mainline passed (a few needed adjustments). #30 Crossover near the Coaling Tower had a tight spot removed (Shinohara). Still working #23 (Shinohara) next to Sand House, some tightness and maybe rail alignment issues to TT track. Noted that the Sand House foundation is too close to track. Also, Coaling Tower Office also too tight to track, about 1/128th inch to K-36 cab shade. Remaining DG switches to test are #10A - #17 in Transfer Yard, Car Shops, NG turntable & ashpit.

    Extras

  • KentS replaced blown Heater fuse in box at Royal Gorge.
  • KentS installed LED bulb in exterior light and deactivated day/night switch.

  • 9 November 2022    Crew: GaryM & DanielS

    Salida
    GaryM continued switch testing with K-36 #480. DG Switches #2, #2A, #2B all had tight NG & SG points and failed testing. DG Switch #2B was repaired by filing rail at the tight locations and passed. These three DG switches are the 3 primary, critical switches from the NG arrival/departure track and mainline leading west to the Arkansas River bridge.

    Extras

  • GaryM & DanielS inventoried the NG high side gondolas.
  • A full complement of 28 high side gons were set out for Monarch, and additional waybills were made. This is up from the 20 cars previously assigned to Monarch branch.
  • DanielS pulled ten duplicate car #s from his high side gons to renumber, and GaryM took one of AlexM's.
  • Some Carcards were noted for rework.

  • 5 November 2022    Crew: GaryM, KentS, GrantC & DanielS

    Monarch
    Staged train with K-36s and 14 cars.
            

    Extras

  • Bill Lund visited and toured the layout for the 2023 National Narrow Gauge Convention in Denver next fall.

  • 2 November 2022    Crew: GaryM, KentS, DustyT & DanielS

    Portland
    Buildings back in place until track re-design is begun.
      

    Gorge
    GaryM made some minor repairs on one of the bridge supports and re-installed. DanS has been building the wood waterpipe, seen in the lower left of the photo.
         

    Poncha Junction
    DanielS has got the Charcoal Kilns built and installed. Overall, the entire location has been improved and developed. DanielS and GaryM re-located the Water Tank and pump house to make more distance to the Mears Tank, which also should be on the mainline prior to the 3-Way switch.
                     

    Otto
    DustyT has made huge progress re-shaping the terrain at the Otto bridge and adding the creek.
      

    Tank 7
      

    Parlin
         

    Gunnison
         

    Crested Butte
    GerryG has been making progress on the backdrop at the Big Mine.
                  


    26 October 2022    Crew: GaryM, KentS, DustyT & DanielS

    Salida
    GaryM fine-tuned some handlaid DG switches. A lot of the early DG switches GaryM built were not "notched" for the points. Although the Blackstone engines have traversed these without issues, now that we have brass locos available, that has not been the case. GaryM's K-36 #480 has been christened as "Track Tester", with its especially finicky precision scale tender trucks (similar to the MMIs). Each DG switch is now undergoing painstakening testing with #480, with adjustments made to the switch as necessary, currently in the Salida yard.

    Poncha Junction
    DanielS continued working on the Charcoal Kiln scenery.


    24 September 2022    

    Mears Junction
    Issues noted on the Otto Bridge: Tight spots, vertical track misalignment on "west" end.
      

    Grays
    TomG completed the new bridge/rails on Grays Creek.
      


    10 September 2022    

    Grays
    After determining several issues on the Grays Creek trestle: less than 24" radius, curve misalignment, vertical lean to outside of curve, TomG removed the track, bridge deck and roadbed to effect repairs.
            


    20 July 2022    

    Barrel
    GaryM continued ballast repair and new ballast from Cleora to the Barrel site.
      

    Poncha Junction
    DustyT rescuplted the landscape at the Otto Bridge to make sense of the terrain.
      

    Gunnison
    KentS built a two-sided filler backdrop between the layout and rear wall beam, to backdrop the Gunnison drop-shelf, the Crested Butte Big Mine Extension track, and the Baldwin Branch drop-shelf, as well.
      


    6 July 2022    Crew: GaryM, KentS, TomG, DanielS & DustyT

    Extras

  • KentS & DustyT replaced the fluorescent overhead tubes with LEDs.
         

  • 15 June 2022    

    Extras

  • TomG refinished the north A/C wood panel.
      

  • 26 March 2022    

    Baldwin Branch
    KentS and TomG continued construction on the new Baldwin Branch.
         


    23 March 2022    

    Crested Butte Branch
    GerryG working on the CF&I Big Mine backdrop.
      


    19 March 2022    

    Baldwin Branch
    KentS and TomG getting a lot of benchwork up.
               


    16 March 2022    

    Baldwin Branch
    Spline roadbed clamped & glued.
      


    12 March 2022    Chow: GaryM, GrantC, TomG & DanielS
    12 March 2022    Crew: GaryM, GrantC, TomG & DanielS

    Salida
    GaryM cleaned up ties from excess ballast on ties at the narrowgauge roundhouse.

    Poncha Junction
    DanielS worked on the freight station platform.

    Baldwin Branch
    TomG planed the spline subroadbed on the Castleton run.


    9 March 2022    Crew: GaryM, TomG & KentS

    Salida
    GaryM completed ballasting at the narrowgauge roundhouse.

    Baldwin Branch
    TomG & KentS levelled the spline subroadbed on the Castleton run.


    5 March 2022    Crew: GaryM, GlennG, TomG & KentS

    Salida
    GaryM laid more ballast at the narrowgauge roundhouse.
      

    Gunnison
    GlennG began working some scenery on the grounds.
      

    Baldwin Branch
    KentS and TomG installed the first section of spline for the mainline from the dropshelf to Castleton.
      


    2 March 2022    Crew: GaryM, DanielS, TomG & KentS

    Salida
    GaryM added to the scenery between roundhouses and laid the first section of ballast at the narrowgauge roundhouse.
         

    Poncha Junction
    DanielS continued work on the Warehouse.
      

    Baldwin Branch
    KentS and TomG installed risers along the Castleton and Kubler runs.
      


    26 February 2022    Crew: GaryM, StuJ, GrantC, TomG & KentS

    Crested Butte
    StuJ scratchbuilt this shop from current buildings located in town.
      


    19 February 2022    Crew: GaryM, DanielS, TomG & KentS

    Salida
    GaryM worked on ground cover scenery around the narrowgauge roundhouse foundation.
      

    Poncha Junction
    DanielS continued work on the Warehouse.
      

    Baldwin Branch
    KentS and TomG built the benchwork connecting the wye corner to the Kubler mine corner.
            


    5 February 2022    Crew: GaryM, GrantC, DanielS, TomG, GerryG & KentS

    Salida
    GaryM added ground dirt to the roundhouse and installed the sandhouse foundation.
      

    Poncha Junction
    DanielS painting warehouse interior.
      

    Crested Butte
    GerryG painted the ridgeline and mountains above the tipple.
         

    Baldwin Branch
    KentS and TomG built the Kubler mine corner.
            


    8 January 2022    Crew: GaryM

    Salida
    GaryM puttied around the turntable foundation.
      



    2021 Status Reports2020 Status Reports2019 Status Reports
    2018 Status Reports2017 Status Reports2016 Status Reports
    2015 Status Reports2012 Status Reports2009 Status Reports
    2014 Status Reports2011 Status Reports2008 Status Reports
    2013 Status Reports2010 Status Reports2007 Status Reports







    Return to Scenic Line Modeler's Home           This page last modified 28 December 2022.