 The tender draft
box area had to be built up and reworked due to deterioration. |
 The tender end sill
had to be completely remanufactured due to rust and deterioration. |
 More boiler braces
are brought out of storage for sandblasting and repairs if needed. |
 Brake rigging. |
 Both tender trucks
required spring hanger gusset repairs due to excessive wear. This is the
same area show in photo 36 after repairs. |
 Work continues on
the tender frame. |
 A view of the newly
fabricated valve gear link block. Here you can see the lubrication
passages that had to be machined into the blocks. |
 Another view of the
link block. |
 The stocker
elevator pipe assembly is brought back into the shop for initial fitting
to the locomotive frame. |
 The elevator pipe
assembly has been brought over next to the locomotive frame prior to
attaching it to the locomotive. |
 The elevator pipe
support is temporarily attached to the mud ring and back-head to check
for proper fit and alignment prior to attaching the elevator pipe.
|
 A view of the
elevator pipe support from the rear of the locomotive frame. |
 One of four bolt
mounting hole that required filling in due to excessive ware. The hole
will later be drilled to the proper size prior to final assembly. The
welding was performed by volunteer Charles Cantrell. |
 Close up of another
weld. |
 The inner door
sheet (back sheet) and back-head are remounted on the locomotive in
preparation for fabricating a new boiler wrapper sheet section. |
 The old back-head
has been resurrected as a jig to fabricate the new roof sheet and
back-head patch section. You can see, what will become, the new roof
sheet section mounted in the jig prior to forming. |
 Contractor Bill
Frederickson starts the initial heating of the sheet while Walter
Elvidge slowly applys tension on the chain host to start the bending
process. |
 Volunteers Chad
Frederickson and Charles Cantrell keep the heat on while Walter Elvidge
continues to apply tension with the chain hoists.
|
 Bill holds a
flattening hammer while Jeff Kemmer swings the sledge. The continuous
movement and positioning of the flattening hammer and the subsequent
blows of the sledge slowly start the sheet to form to the desired
shape.
|
 A side view of the
previous process. |
 The shaping process
continues. |
 Bill directs Walter
while Chad keeps the heat on the opposite side of the sheet. |
 The heating process
continues. |
 Chad and Jeff
heating the sheet while I apply tension to the chain hoists. |
 After a round of
hammering, Jeff takes over torch duty from Chad. Chad will now take over
the hammer while Bill continues to hold the flattening hammer. |
 Chad and Bill
working as a team while I continue to keep tension on the chains. Walter
and Jeff take a few moments break from the extreme heat. |
 A view of the
completed sheet. It has been trimmed initially to fit the location where
it will be installed. |
 A view from the
engineer’s side of the sheet. |
 The pony truck is
rolled back into the shop for additional repairs. |
 The pony trucks
transom bushing locations were deteriorated. The transom required
machining to accept new bushing and pins. Here you can see the completed
machining. |
 A close up of the
completed machining. New bushings and pins will be fabricated in the
machine shop. |
 Volunteers Tom
Diehl and John Fauzio taper ream rigid staybolt locations on the inner
throat-sheet due to excess thread wear. The holes will later be welded
then drilled and threaded to the correct size for the new staybolts. |